Timeline

  • Dec 4, 2018

    Completed the purchase of 1140 Yonge Street

    December 4th, 2018

  • Aug 19, 2019

    Pre-application meeting with City Staff

    August 19th, 2019 - The project team met with City Staff to introduce our concept and vision for 1140 Yonge including architectural design, heritage, sustainability and public realm

  • Aug 20, 2019

    Meeting with Neighbours #1

    August 20th 2019 - We met with immediate neighbours to introduce our concept and vision for 1140 Yonge as well as boundary conditions and the construction process

  • Sep 23, 2019

    Meeting with Neighbours #2

    September 23rd 2019 - We met with immediate neighbours to introduce our concept and vision for 1140 Yonge as well as boundary conditions and the construction process

  • Sep 24, 2019

    Meeting with Rosedale Mainstreet Business Improvement Area (BIA)

    September 24th, 2019 - We met with the Rosedale Mainstreet BIA Executive to introduce our concept and vision for 1140 Yonge 

  • Sep 26, 2019

    Meeting with Councillor Layton

    September 26th, 2019 - The project team met with Councillor Layton, and City Staff, to introduce our 15-storey concept and vision for 1140 Yonge as well as our approach to community engagement  

  • Oct 11, 2019

    Meeting with Neighbours #3

    October 11th, 2019 - We met with immediate neighbours to introduce our concept and vision for 1140 Yonge as well as boundary conditions and the construction process

  • Oct 25, 2019

    Meeting with Neighbours #4

    October 25th, 2019 - We met with immediate neighbours to introduce our concept and vision for 1140 Yonge as well as boundary conditions and the construction process

  • Oct 11, 2019

    Meeting with ABC Residents’ Association (RA)

    October 21st, 2019 - The project team presented our vision and concept for 1140 Yonge to a large contingent of the ABC RA, obtained initial feedback on the proposal and suggested an approach for structuring ongoing engagement

  • Oct 21, 2019

    Meeting with South Rosedale RA (SRRA)

    November 4th, 2019 - We met with executives of SRRA to introduce our 15-storey concept and vision for 1140 Yonge as well as our approach to community engagement

  • Nov 12, 2019

    Meeting with Summerhill RA (SRA)

    November 12th, 2019 - The project team presented our vision and concept for 1140 Yonge to a large contingent of the SRA, obtained initial feedback on the proposal and suggested an approach for structuring ongoing engagement

  • Jan 29, 2020

    Second Pre-Application Meeting with City Staff

    January 29th, 2020 - We met with City Staff for a second time to provide an update on community consultation, present some updates to the 15-storey building massing and to discuss next steps

  • Feb 20, 2020

    Second Meeting with ABC RA

    February 20th, 2020 - We met with ABC RA executive for a second time to present some updates to the building massing and discuss next steps on community consultation

  • Mar 4, 2020

    Meeting with Neighbours #5

    March 4th, 2020 - We met with immediate neighbours to introduce our concept and vision for 1140 Yonge as well as boundary conditions and the construction process

  • Feb 20, 2020

    Third Pre-Application Meeting with Staff

    June 16, 2020 - We met with City Staff to introduce a revised concept at 13-storeys, incorporating 1134 Yonge St, refining the proposed townhomes along Marlborough, and providing greater setbacks and terracing to the surrounding neighbourhood

  • Feb 20, 2020

    Third Meeting with ABC RA

    May 8th, 2020 - We met with ABC RA executive for a third time to present some updates to the 13-storey building massing and discuss next steps on community consultation

  • Jun 3, 2020

    First Planning Application Submission

    Submitted September 2, 2020

  • Jun 3, 2020

    Statutory Public Meeting on First Planning Application

    November 17, 2020 - We participated in City-led Community Consultation Meeting and facilitated discussion on built form, traffic, parking & access, architecture & design, as well as heritage.